April 2026

Please note the following construction projects will affect vehicular or pedestrian mobility around campus during the upcoming month of April 2026. For more regularly updated reference, this information can also be viewed at the facilities website and as an interactive map.

Project Name: Bonnie Brae Street Widening
  • Areas Impacted: Vehicular traffic to Mean Green Village will be intermittently disrupted. Traffic to DATCU Stadium and Victory Hall may be disrupted. No pedestrian access.
  • Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr
  • Project Summary:  Installation of underground utilities and roadway expansion to four-lane divided highway.
  • Project Manager: City of Denton
  • Project Start Date: 2024-01-01
  • Project End Date: 2026-12-31

Project Name: Bernard Street Roadwork
  • Areas Impacted: Automobile traffic will be disrupted throughout the project. Crosswalks may not be accessible.
  • Location Description: Bernard Street between Hickory and Chestnut
  • Project Summary:  Utilities replacement and road reconstruction 
  • Project Manager: City of Denton
  • Project Start Date: 2026-02-04
  • Project End Date: 2026-07-01

Project Name: Science and Tech. Building
  • Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.
  • Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
  • Project Summary:  Construction of new Science and Tech. building.
  • Project Manager: UNT System
  • Project Start Date: 2024-09-01
  • Project End Date: 2026-09-01

Project Name: Lot 40 Renovations
  • Areas Impacted: Parking in Lot 40 and Greek Life Center may be intermittently disrupted. Lot 40 access from Highland Street only. Sidewalk access along Maple Street.
  • Location Description: Lot 40
  • Project Summary:  Renovation of parking lot
  • Project Manager: UNT Facilities
  • Project Start Date: 2026-03-25
  • Project End Date: 2026-08-01
Project Name: Sage Hall Exterior Restoration
  • Areas Impacted: West entrance will be temporarily obstructed. Entry to Sage Hall is accessible at north and south entrances.
  • Location Description: West entrance of Sage Hall
  • Project Summary: Restoring building exterior
  • Project Manager: UNT Facilities
  • Project Start Date: 2026-04-06
  • Project End Date: 2026-04-09

Project Name: Mulberry Street Utilities
  • Areas Impacted: Mulberry Street between Ave C and D closed to all automobile and pedestrian traffic. Parking on Avenue D may be disrupted throughout the project.
  • Location Description: Mulberry Street between Avenue C and Avenue D, and Avenue D between Hickory and Sycamore
  • Project Summary: Upgrading water utilities
  • Project Manager: City of Denton
  • Project Start Date: 2026-04-13
  • Project End Date: 2026-05-26

Historical Construction Obstruction Reports

March 2026

Please note the following construction projects will affect vehicular or pedestrian mobility around campus during the upcoming month of March 2026. For more regularly updated reference, this information can also be viewed at the facilities website and as an interactive map.

Project Name: South Bonnie Brae Street Widening
  • Areas Impacted: Vehicular traffic to Mean Green Village will be intermittently disrupted. Traffic to DATCU Stadium and Victory Hall may be disrupted. No pedestrian access.
  • Project Manager: City of Denton
  • Project Start Date: 2024-01-01
  • Project End Date: 2026-12-31
  • Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr
  • Project Summary:  Installation of underground utilities and roadway expansion to four-lane divided highway.
Project Name: North Bonnie Brae Street Widening
  • Areas Impacted: Travel between Main Campus and Discovery Park will be disrupted throughout project duration and may need to be rerouted.
  • Project Manager: City of Denton
  • Project Start Date: 2026-02-02
  • Project End Date: 2026-03-13
  • Location Description: Bonnie Brae between Riney Road and US-77/Elm Street
  • Project Summary:  Installation of underground utilities and roadway expansion to four-lane divided highway.
Project Name: Bernard Street Roadwork
  • Areas Impacted: Automobile traffic will be disrupted throughout the project. Crosswalks may not be accessible.
  • Project Manager: City of Denton
  • Project Start Date: 2026-02-04
  • Project End Date: 2026-07-01
  • Location Description: Bernard Street between Hickory and Chestnut
  • Project Summary:  Utilities replacement and road reconstruction  
Project Name: Science and Tech. Building
  • Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.
  • Project Manager: UNT System
  • Project Start Date: 2024-09-01
  • Project End Date: 2026-09-01
  • Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
  • Project Summary:  Construction of new Science and Tech. building.
Project Name: Clark Park Electrical Lines
  • Areas Impacted: Sidewalk and pedestrian access to Clark Park may be intermittently disrupted.
  • Project Manager: Carl Parsons
  • Project Start Date: 2026-01-16
  • Project End Date: 2026-03-06
  • Location Description: Maple Street and Clark Park
  • Project Summary:  Upgrades to electrical distribution and replacement of overhead lines
Project Name: Bruce Hall Courtyard
  • Areas Impacted: Pedestrian traffic will be diverted around the area for the duration of the project.
  • Project Manager: UNT Facilities
  • Project Start Date: 2026-01-19
  • Project End Date: 2026-03-27
  • Location Description: Courtyard and sidewalk between Bruce Hall and Life Sciences Complex
  • Project Summary:  Upgrades to drainage and sidewalk replacement
Project Name: Life Science Bioswale
  • Areas Impacted: Pedestrian access to the area may be intermittently disrupted.
  • Project Manager: Brandon Lacy
  • Project Start Date: 2026-03-02
  • Project End Date: 2026-08-31
  • Location Description: Retention Bioswale at Life Science Complex
  • Project Summary:  Renovation of drainage and landscaping
Project Name: Highland Garage Landscaping
  • Areas Impacted: Vehicular and pedestrian traffic may be intermittently disrupted.
  • Project Manager: Brandon Lacy
  • Project Start Date: 2026-03-02
  • Project End Date: 2026-04-24
  • Location Description: Highland Street between Avenue A and Central
  • Project Summary:  Renovation of landscaping
February 2026

Project Name: Bruce Hall Courtyard

Areas Impacted: Pedestrian traffic will be diverted around the area for the duration of the project.

Project Manager: UNT Facilities
Project Start Date: 2026-01-19
Project End Date: 2026-02-13
Location Description: Courtyard and sidewalk between Bruce Hall and Life Sciences Complex
Project Summary:  Upgrades to drainage and sidewalk replacement

Project Name: Clark Park Electrical

Areas Impacted: Sidewalk and pedestrian access to Clark Park may be intermittently disrupted.

Project Manager: Carl Parsons
Project Start Date: 2026-01-16
Project End Date: 2026-02-27
Location Description: Maple Street and Clark Park
Project Summary:  Upgrades to electrical distribution and replacement of overhead lines

Project Name: Science and Tech. Building

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

Project Manager: UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
Project Summary:  Construction of new Science and Tech. building.

Project Name: Bonnie Brae Street Widening

Areas Impacted: Vehicular traffic to Mean Green Village will be intermittently disrupted. Traffic to DATCU Stadium and Victory Hall may be disrupted. No pedestrian access.

Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr
Project Summary:  Installation of underground utilities and roadway expansion to four-lane divided highway.

Project Name: Prairie Street Roadwork

Areas Impacted: Automobile traffic impacted on Prairie St between Bernard and Welch. Crosswalks may not be accessible.

Project Manager: City of Denton
Project Start Date: 2025-11-05
Project End Date: 2026-03-05
Location Description: Prairie Street between Bernard and Welch
Project Summary:  Utilities replacement and road reconstruction 

Project Name: Bernard Street Roadwork

Areas Impacted: Automobile traffic will be disrupted throughout the project. Crosswalks may not be accessible.

Project Manager: City of Denton
Project Start Date: 2026-01-30
Project End Date: 2026-07-24
Location Description: Bernard Street between Hickory and Chestnut
Project Summary:  Utilities replacement and road reconstruction  

January 2026

Project Name: Sycamore and Welch Construction

Areas Impacted: Intersection will not be accessible to vehicular traffic during construction. Pedestrian crosswalks may not be available.

Project Manager: City of Denton
Project Start Date: 2025-12-15
Project End Date: 2026-01-10
Location Description: Intersection of Sycamore and Welch
Project Summary:  Installation of Traffic Control signals. Will be completed prior to Spring semester 2026.

 Project Name: Pollinative Prairie Walkway

Areas Impacted: Vehicular travel along Discovery Park ring road may be temporarily disrupted during construction.

Project Manager: Brandon Lacy
Project Start Date: 2025-08-04
Project End Date: 2026-01-09
Location Description: Discovery Park Pollinative Prairie
Project Summary:  Addition of covered pavilion and seating for Pollinative Prairie at Discovery Park campus. Will be completed prior to Spring semester 2026.

Project Name: Prairie Street Construction

Areas Impacted: Automobile traffic impacted on Prairie St between Bernard and Welch. Crosswalks may not be accessible.

Project Manager: City of Denton
Project Start Date: 2025-11-05
Project End Date: 2026-03-31
Location Description: Prairie Street between Bernard and Welch
Project Summary:  Utilities replacement and road reconstruction.

Project Name: Bonnie Brae St Widening

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street between Airport Rd and Roselawn Dr
Project Summary:  Installation of underground utilities and roadway expansion to four-lane divided highway.

Project Name: Science and Tech. Building

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

Project Manager: UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
Project Summary:  Construction of new Science and Tech. building.

December 2025

Project Name: Bonnie Brae St Widening

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr
Project Summary:  Installation of underground utilities and roadway expansion to four-lane divided highway.

Project Name: Welch St Construction

Areas Impacted: No automobile traffic on Welch St between Prairie and Highland. No crosswalk available. Pedestrian crosswalk at Central and Highland.

Project Manager: City of Denton
Project Start Date: 2025-09-15
Project End Date: 2025-11-26
Location Description: Welch Street between Prairie and Highland
Project Summary:  Utilities replacement and road reconstruction

Project Name: Welch St Construction

Areas Impacted: No automobile traffic on Welch St between Hickory and Mulberry. No accessible crosswalk at Mulberry and Welch.

Project Manager: City of Denton
Project Start Date: 2025-10-01
Project End Date: 2025-12-05
Location Description: Welch Street between Hickory and Mulberry
Project Summary:  Utilities replacement and road reconstruction

Project Name: Prairie St Construction

Areas Impacted: No automobile traffic on Prairie St between Bernard and Welch. Crosswalks may not be accessible.

Project Manager: City of Denton
Project Start Date: 2025-11-05
Project End Date: 2026-03-31
Location Description: Prairie Street between Bernard and Welch
Project Summary:  Utilities replacement and road reconstruction

Project Name: Sycamore and Welch Construction

Areas Impacted: Intersection will not be accessible to vehicular traffic during construction. Pedestrian crosswalks may not be available.

Project Manager: City of Denton
Project Start Date: 2025-12-15
Project End Date: 2026-01-10
Location Description: Intersection of Sycamore with Welch
Project Summary:  Installation of Traffic Control signals

Project Name: Union Circle and Welch Construction

Areas Impacted: Intersection will not be accessible to vehicular traffic during construction. Pedestrian crosswalks may not be available.

Project Manager: City of Denton
Project Start Date: 2025-12-20
Project End Date: 2026-01-03
Location Description: Intersection of Chestnut/Union Circle with Welch
Project Summary:  Installation of Traffic Control signals

Project Name: Avenue C Lighting Installation

Areas Impacted: Vehicle traffic southbound on Avenue C will be redirected between Chestnut and Maple. Northbound traffic may be temporarily disrupted. Sidewalks are not affected.

Project Manager: Carl Parsons
Project Start Date: 2025-11-24
Project End Date: 2025-11-26
Location Description: Avenue C Southbound Lane
Project Summary:  Installation of new street lighting masts

 Project Name: Performing Arts Electrical

Areas Impacted: Minimal automobile and pedestrian impact. Trenches will be dug around the north side of the buildings. Sidewalk access may be impacted intermittently.

Project Manager: Carl Parsons
Project Start Date: 2025-10-01
Project End Date: 2025-11-30
Location Description: Performing Arts Center and Annex
Project Summary:  Upgrading electrical infrastructure to Performing Arts Center

Project Name: Bruce Hall Lighting Installation

Areas Impacted: Walkway between Bruce and Life Science will be intermittently disrupted.

Project Manager: Carl Parsons
Project Start Date: 2025-10-29
Project End Date: 2025-11-26
Location Description: Walkway between Bruce and Life Science
Project Summary:  Installation of electrical infrastructure and lighting masts

Project Name: Highland Street Closure

Areas Impacted: Vehicle traffic must be pre-approved. Pedestrian access is not impacted.

Project Manager: UNT Facilities
Project Start Date: 2025-08-18
Project End Date: 2026-01-01
Location Description: Highland Street between Ave C and Ave A
Project Summary:  Highland Street is pedestrian-only through the center of campus. Non-approved traffic will be redirected.

Project Name: Science and Tech. Building

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

Project Manager: UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
Project Summary:  Construction of new Science and Tech building.

Project Name: Hickory Street Landscaping

Areas Impacted: Sidewalks along Hickory and leading into Hickory, Auditorium, and Language buildings may be intermittently disrupted.

Project Manager: Brandon Lacy
Project Start Date: 2025-08-01
Project End Date: 2026-01-01
Location Description: Hickory, Auditorium, and Language building north lawns
Project Summary:  Raising sidewalks and renovation of irrigation and landscaping.

Project Name: Softball Clubhouse Construction

Areas Impacted: Use of softball fields and batting facilities will be disrupted during construction.

Project Manager: UNT System
Project Start Date: 2025-02-03
Project End Date: 2025-12-31
Location Description: Mean Green Village Softball Field
Project Summary:  Improvement of dugouts and construction of new club house and offices.

Project Name: Sullivant Public Safety Center Parking Canopy

Areas Impacted: Minimal pedestrian impact, police parking will be disrupted.

Project Manager: Herman McKeiver
Project Start Date: 2025-09-01
Project End Date: 2025-12-31
Location Description: Sullivant Public Safety Center
Project Summary:  Installation of parking canopy along west side of Sullivant.

Project Name: Pollinative Prairie Walkway

Areas Impacted: Vehicular travel along Discovery Park ring road may be temporarily disrupted during construction.

Project Manager: Brandon Lacy
Project Start Date: 2025-08-04
Project End Date: 2025-11-21
Location Description: Discovery Park Pollinative Prairie
Project Summary:  Addition of covered sidewalk and benches at Pollinative Prairie at Discovery Park campus.

Thanksgiving Week 2025

Highland and Welch Construction

Areas Impacted: The intersection of Highland and Welch will be closed for 24 hours. Local and bus traffic will be redirected. Sidewalks may be disrupted.

 Project Manager: City of Denton

Start Date: November 24, 2025

End Date: November 26, 2025

Location Description: Intersection of Highland and Welch

Project Summary: Installation of utilities and road reconstruction

 

November 2025

Project Name: Bonnie Brae St Widening

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr
Project Summary: Installation of underground utilities and roadway expansion to four-lane divided highway.

Project Name: Welch St Construction

Areas Impacted: No automobile traffic on Welch St between Prairie and Highland. No crosswalk available. Pedestrian crosswalk at Central and Highland.

Project Manager: City of Denton
Project Start Date: 2025-09-15
Project End Date: 2025-11-24
Location Description: Welch Street between Prairie and Highland
Project Summary: Utilities replacement and road reconstruction

Project Name: Welch St Construction

Areas Impacted: No automobile traffic on Welch St between Hickory and Mulberry. No accessible crosswalk at Mulberry and Welch.

Project Manager: City of Denton
Project Start Date: 2025-10-01
Project End Date: 2026-01-02
Location Description: Welch Street between Hickory and Mulberry
Project Summary: Utilities replacement and road reconstruction

 Project Name: Highland Street Closure

Areas Impacted: Vehicle traffic must be pre-approved. Pedestrian access is not impacted.

Project Manager: UNT Facilities
Project Start Date: 2025-08-18
Project End Date: 2026-01-01
Location Description: Highland Street between Ave C and Ave A
Project Summary: Highland Street is pedestrian-only through the center of campus. Non-approved traffic will be redirected.

 Project Name: Science and Tech. Building

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

Project Manager: Jay Henson, UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
Project Summary: Construction of new Science and Tech. building.

Project Name: Hickory Street Landscaping

Areas Impacted: Sidewalks along Hickory and leading into Hickory, Auditorium, and Language buildings may be intermittently disrupted.

Project Manager: Brandon Lacy
Project Start Date: 2025-08-01
Project End Date: 2026-01-01
Location Description: Hickory, Auditorium, and Language building north lawns
Project Summary: Raising sidewalks and renovation of irrigation and landscaping.

Project Name: Performing Arts Electrical

Areas Impacted: Minimal automobile and pedestrian impact. Trenches will be dug around the north side of the buildings. Sidewalk access may be impacted intermittently.

Project Manager: Carl Parsons
Project Start Date: 2025-10-01
Project End Date: 2025-11-30
Location Description: Performing Arts Center and Annex
Project Summary: Upgrading electrical infrastructure to Performing Arts Center

Project Name: Intramural Fields Lighting and Irrigation Installation

Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street

Project Manager: Herman McKeiver
Project Start Date: 2024-08-01
Project End Date: 2025-11-02
Location Description: Intramural Fields at Bonnie Brae and Prairie
Project Summary: Construction of new field lighting and irrigation systems for intramural fields

Project Name: Softball Clubhouse Construction

Areas Impacted: Use of softball fields and batting facilities will be disrupted during construction.

Project Manager: Jay Henson, UNT System
Project Start Date: 2025-02-03
Project End Date: 2025-12-31
Location Description: Mean Green Village Softball Field
Project Summary: Improvement of dugouts and construction of new club house and offices.

Project Name: Pollinative Prairie Walkway

Areas Impacted: Vehicular travel along Discovery Park ring road may be temporarily disrupted during construction.

Project Manager: Brandon Lacy
Project Start Date: 2025-08-04
Project End Date: 2025-11-21
Location Description: Discovery Park Pollinative Prairie
Project Summary: Addition of covered sidewalk and benches at Pollinative Prairie at Discovery Park campus.

Project Name: Sullivant Public Safety Center Parking Canopy

Areas Impacted: Minimal pedestrian impact, police parking will be disrupted.

Project Manager: Herman McKeiver
Project Start Date: 2025-09-01
Project End Date: 2025-12-31
Location Description: Sullivant Public Safety Center
Project Summary: Installation of parking canopy along west side of Sullivant.

 

October 2025

Project Name: Bonnie Brae Street Widening

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr
Project Summary:  Installation of underground utilities and roadway expansion to four-lane divided highway.

Project Name: Science and Tech. Building

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

Project Manager: UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
Project Summary:  Construction of new Science and Tech. building.

Project Name: Union Circle Realignment

Areas Impacted: Union Circle. Impacts access to the University Union, Matthews Hall Annex, Union Circle Garage, Radio TV and Performing Arts Building, Lot 50, and Lot 37.

Project Manager: City of Denton
Project Start Date: 2025-05-14
Project End Date: 2025-10-01
Location Description: Union Circle
Project Summary:  Street reconstruction and realignment. Traffic flow on Union Circle will be reversed.

Project Name: Welch Street Construction

Areas Impacted: No automobile traffic on Welch St between Hickory and Mulberry. No accessible crosswalk at Mulberry and Welch.

Project Manager: City of Denton
Project Start Date: 2025-10-06
Project End Date: 2025-12-24
Location Description: Welch Street between Hickory and Mulberry
Project Summary:  Utilities replacement and road reconstruction.

Project Name: Welch Street Construction

Areas Impacted: No automobile traffic on Welch St between Prairie and Highland. No crosswalk available. Pedestrian crosswalk at Central and Highland.

Project Manager: City of Denton
Project Start Date: 2025-09-15
Project End Date: 2025-11-24
Location Description: Welch Street between Prairie and Highland
Project Summary:  Utilities replacement and road reconstruction.

Project Name: Fry and Hickory Lighting

Areas Impacted: Pedestrian crosswalks may be disrupted during construction. Accessible pathways may not be available.

Project Manager: City of Denton
Project Start Date: 2025-09-01
Project End Date: 2025-12-22
Location Description: Intersection of Hickory Street with Fry Street and Avenue A
Project Summary:  Upgrading intersection lighting and crosswalks.

Project Name: Softball Clubhouse Construction

Areas Impacted: Use of softball fields and batting facilities will be disrupted during construction.

Project Manager: UNT System
Project Start Date: 2025-02-03
Project End Date: 2025-12-31
Location Description: Mean Green Village Softball Field
Project Summary:  Improvement of dugouts and construction of new club house and offices.

Project Name: Intramural Fields Lighting and Irrigation Installation

Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street

Project Manager: Herman McKeiver
Project Start Date: 2024-08-01
Project End Date: 2025-10-02
Location Description: Intramural Fields at Bonnie Brae and Prairie
Project Summary:  Construction of new field lighting and irrigation systems for intramural fields.

Project Name: GAB Sidewalk Improvements

Areas Impacted: Pedestrian access to GAB from the west will be disrupted throughout the project.

Project Manager: Randy Salsman
Project Start Date: 2025-09-22
Project End Date: 2025-10-24
Location Description: Courtyard West of General Academic Building
Project Summary:  Replace and raise concrete sidewalks.

Project Name: Sullivant Public Safety Center Parking Canopy

Areas Impacted: Minimal pedestrian impact, police parking will be disrupted.

Project Manager: Herman McKeiver
Project Start Date: 2025-09-01
Project End Date: 2025-12-31
Location Description: Sullivant Public Safety Center
Project Summary:  Installation of parking canopy along west side of Sullivant.

Project Name: Pollinative Prairie Walkway

Areas Impacted: Vehicular travel along Discovery Park ring road may be temporarily disrupted during construction.

Project Manager: Brandon Lacy
Project Start Date: 2025-08-04
Project End Date: 2025-11-21
Location Description: Discovery Park Pollinative Prairie
Project Summary:  Addition of covered sidewalk and benches at Pollinative Prairie at Discovery Park campus.

Project Name: Highland Street Closure

Areas Impacted: Vehicle traffic must be pre-approved. Pedestrian access is not impacted.

Project Manager: UNT Facilities
Project Start Date: 2025-08-18
Project End Date: 2026-01-01
Location Description: Highland Street between Ave C and Ave A
Project Summary:  Highland Street is pedestrian-only through the center of campus. Non-approved traffic will be redirected.

Project Name: Hickory Street Landscaping

Areas Impacted: Sidewalks along Hickory and leading into Hickory, Auditorium, and Language buildings may be intermittently disrupted.

Project Manager: Brandon Lacy
Project Start Date: 2025-08-01
Project End Date: 2025-11-28
Location Description: Hickory, Auditorium, and Language building north lawns
Project Summary:  Renovation of irrigation and landscaping

Project Name: Performing Arts Electrical

Areas Impacted: Minimal automobile and pedestrian impact. Trenches will be dug around the north side of the buildings. Sidewalk access may be impacted intermittently.

Project Manager: Carl Parsons
Project Start Date: 2025-10-01
Project End Date: 2025-11-15
Location Description: Performing Arts Center and Annex
Project Summary:  Upgrading electrical infrastructure to Performing Arts Center.

Project Name: Music Building Plumbing Upgrade

Areas Impacted: Pedestrian crosswalk not available. Building entrances are not affected.

Project Manager: UNT Facilities
Project Start Date: 2025-09-19
Project End Date: 2025-10-10
Location Description: South courtyard crosswalk at Music Building
Project Summary:  Upgrading hot water infrastructure for Music Building.

September 2025

Project Name: Bonnie Brae Street Widening

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street, from Airport Road to Roselawn Drive
Project Summary:  Installation of underground utilities and roadway expansion to four-lane divided highway.

Project Name: Science and Tech. Building

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

Project Manager: UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street
Project Summary:  Construction of new Science and Tech. building.

Project Name: Union Circle Realignment
Areas Impacted: Union Circle. Impacts access to the University Union, Matthews Hall Annex, Union Circle Garage, Radio TV and Performing Arts Building, Lot 50, and Lot 37.

Project Manager: City of Denton
Project Start Date: 2025-05-14
Project End Date: 2025-10-01
Location Description: Union Circle
Project Summary:  Street reconstruction and realignment. Traffic flow on Union Circle will be reversed.

Project Name: Welch Street Construction

Areas Impacted: No automobile traffic on Welch St between Mulberry and Sycamore. No accessible crosswalk at Mulberry and Welch. Pedestrian crosswalk at Sycamore.

Project Manager: City of Denton
Project Start Date: 2025-07-07
Project End Date: 2025-10-01
Location Description: Welch Street between Mulberry and Sycamore
Project Summary:  Utilities replacement and road reconstruction.

Project Name: Welch Street Construction

Areas Impacted: No automobile traffic on Welch St between Prairie and Highland. Pedestrian crosswalk at Highland.

Project Manager: City of Denton
Project Start Date: 2025-09-03
Project End Date: 2025-11-24
Location Description: Welch Street between Prairie and Highland
Project Summary:  Utilities replacement and road reconstruction.Project Name: Welch and Chestnut Traffic Signals

Areas Impacted: Intersection of Welch with Chestnut and Union Circle will be closed to vehicular and pedestrian traffic. No accessible crosswalk available during construction.

Project Manager: City of Denton
Project Start Date: 2025-09-17
Project End Date: 2025-09-19
Location Description: Intersection of Welch and Chestnut Streets
Project Summary:  Installation of new traffic signals and crosswalks.

Project Name: Welch and Prairie Traffic Signals

Areas Impacted: Intersection of Welch with Prairie and Union Circle will be closed to vehicular and pedestrian traffic. No accessible crosswalk available during construction.

Project Manager: City of Denton
Project Start Date: 2025-09-19
Project End Date: 2025-09-22
Location Description: Intersection of Welch and Prairie Streets
Project Summary:  Installation of new traffic signals and crosswalks.

Project Name: Softball Clubhouse Construction

Areas Impacted: Use of softball fields and batting facilities will be disrupted during construction.

Project Manager: UNT System
Project Start Date: 2025-02-03
Project End Date: 2025-12-31
Location Description: Mean Green Village Softball Field
Project Summary:  Improvement of dugouts and construction of new club house and offices.

Project Name: Intramural Fields Lighting and Irrigation Installation

Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street.

Project Manager: Herman McKeiver
Project Start Date: 2024-08-01
Project End Date: 2025-09-01
Location Description: Intramural Fields at Bonnie Brae and Prairie
Project Summary:  Construction of new field lighting and irrigation systems for intramural fields.

Project Name: Discovery Park Fire Piping Replacement

Areas Impacted: Parking lots and sidewalks leading to Discovery Park will be impacted. Trenches dug in phases around the building exterior.

Project Manager: Carl Parsons
Project Start Date: 2025-02-03
Project End Date: 2026-08-04
Location Description: Discovery Park
Project Summary:  Fire piping to be replaced around building exterior, interior, and installation of water pumps for expanded sprinkler system.

Project Name: Pollinative Prairie Walkway

Areas Impacted: Vehicular travel along Discovery Park ring road may be temporarily disrupted during construction.

Project Manager: Brandon Lacy
Project Start Date: 2025-08-04
Project End Date: 2025-11-21
Location Description: Discovery Park Pollinative Prairie
Project Summary:  Addition of covered sidewalk and benches at Pollinative Prairie at Discovery Park campus.

Project Name: Hickory Street Landscaping

Areas Impacted: Sidewalks along Hickory and leading into Hickory, Auditorium, and Language buildings may be intermittently disrupted.

Project Manager: Brandon Lacy
Project Start Date: 2025-08-01
Project End Date: 2025-11-28
Location Description: Hickory, Auditorium, and Language building north lawns
Project Summary:  Renovation of irrigation and landscaping.

Project Name: Sullivant Public Safety Center Parking Canopy

Areas Impacted: Minimal pedestrian impact, police parking will be disrupted.

Project Manager: Herman McKeiver
Project Start Date: 2025-09-01
Project End Date: 2025-12-31
Location Description: Sullivant Public Safety Center
Project Summary:  Installation of parking canopy along west side of Sullivant.

August 2025

Project Name: Bonnie Brae St Widening

Project Manager: City of Denton
Project Start Date: 2024-01-01
Project End Date: 2026-12-31
Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr
Project Summary:  Installation of underground utilities and roadway expansion to four-lane divided highway.

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

Project Name: Science and Tech. Building

Project Manager: UNT System
Project Start Date: 2024-09-01
Project End Date: 2026-09-01
Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.
Project Summary:  Construction of new Science and Tech. building.

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

Project Name: Intramural Fields Lighting and Irrigation Installation

Project Manager: Herman McKeiver
Project Start Date: 2024-08-01
Project End Date: 2025-09-01
Location Description: Intramural Fields at Bonnie Brae and Prairie
Project Summary:  Construction of new field lighting and irrigation systems for intramural fields

Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street.

Project Name: Discovery Park Fire Piping Replacement

Project Manager: Carl Parsons
Project Start Date: 2025-02-03
Project End Date: 2026-08-04
Location Description: Discovery Park
Project Summary:  Fire piping to be replaced around building exterior, interior, and installation of water pumps for expanded sprinkler system

Areas Impacted: Parking lots and sidewalks leading to Discovery Park will be impacted. Trenches dug in phases around the building exterior.

Project Name: Softball Clubhouse Construction

Project Manager: UNT System
Project Start Date: 2025-02-03
Project End Date: 2025-12-31
Location Description: Mean Green Village Softball Field
Project Summary:  Improvement of dugouts and construction of new club house and offices.

Areas Impacted: Use of softball fields and batting facilities will be disrupted during construction.

Project Name: Mulberry St Construction

Project Manager: City of Denton
Project Start Date: 2024-12-03
Project End Date: 2025-09-01
Location Description: Mulberry Street
Project Summary:  Upgrading city water and sewer lines and street reconstruction.

Areas Impacted: Mulberry St between Welch St and Bernard St. May impact access to Art Annex, University Machine Shop, and Lot 55

Project Name: Welch St Construction

Project Manager: City of Denton
Project Start Date: 2025-03-13
Project End Date: 2025-08-01
Location Description: Welch St between Highland St and Maple St
Project Summary:  Road reconstruction

Areas Impacted: No automobile traffic on Welch St between Maple and Highland. Disrupted crosswalk access at Highland.

Project Name: Chilton Hall Sidewalk Expansion

Project Manager: Brandon Lacy
Project Start Date: 2025-05-12
Project End Date: 2025-08-15
Location Description: Chilton Hall East Side
Project Summary:  Landscaping upgrades and widening of sidewalk in front of Chilton Hall along Avenue C.

Areas Impacted: No sidewalk access along Avenue C. East entrance to Chilton Hall 2nd Floor will not be accessible.

Project Name: Ave D and Chestnut Street Construction

Project Manager: City of Denton
Project Start Date: 2025-05-14
Project End Date: 2025-08-15
Location Description: Intersection of Avenue D and Chestnut Street
Project Summary:  Street reconstruction

Areas Impacted: Ave D between Chestnut and Mulberry, Chestnut Street between Ave D and Ave C. Lot 5 accessible via Sycamore. No sidewalk access along Ave D or Chestnut. Disrupted access for Chestnut and Chilton Halls.

Project Name: Union Circle Realignment

Project Manager: City of Denton
Project Start Date: 2025-05-14
Project End Date: 2025-10-01
Location Description: Union Circle
Project Summary:  Street reconstruction and realignment. Traffic flow on Union Circle will be reversed.

Areas Impacted: Union Circle. Impacts access to the University Union, Matthews Hall Annex, Union Circle Garage, Radio TV and Performing Arts Building, Lot 50, and Lot 37.

Project Name: Highland Garage Landscaping Renovation

Project Manager: Brandon Lacy
Project Start Date: 2025-06-02
Project End Date: 2025-08-08
Location Description: Highland Street Parking Garage
Project Summary:  Maintenance of trees and landscaping and updating irrigation

Areas Impacted: Sidewalk will be closed between Highland Street and the garage. Access to the garage and crosswalk will not be disrupted.

Project Name: Chestnut Hall Landscaping Renovation

Project Manager: Brandon Lacy
Project Start Date: 2025-06-02
Project End Date: 2025-08-15
Location Description: South side of Chestnut Hall
Project Summary:  Renovation of landscaping and irrigation south of Chestnut Hall

Areas Impacted: Pedestrian access to Chestnut Hall from the South may be disrupted.

Project Name: Welch St Construction

Project Manager: City of Denton
Project Start Date: 2025-07-07
Project End Date: 2025-10-01
Location Description: Welch Street between Mulberry and Sycamore
Project Summary:  Utilities replacement and road reconstruction

Areas Impacted: No automobile traffic on Welch St between Mulberry and Sycamore. No pedestrian crosswalk.

Project Name: Discovery Park Sidewalk

Project Manager: Randy Salsman
Project Start Date: 2025-08-01
Project End Date: 2025-08-15
Location Description: Discovery Park Campus
Project Summary:  Addition of sidewalk connecting Elm St to the main building at Discovery Park

Areas Impacted: Automobile traffic may be disrupted entering Discovery Park.

Project Name: GAB Sidewalk Improvements

Project Manager: Randy Salsman
Project Start Date: 2025-08-01
Project End Date: 2025-11-01
Location Description: Courtyard West of General Academic Building
Project Summary:  Replace and raise concrete sidewalks

Areas Impacted: Pedestrian access to GAB from the west will be disrupted throughout the project.

Project Name: Sullivant Public Safety Center Parking Canopy

Project Manager: Herman McKeiver
Project Start Date: 2025-09-01
Project End Date: 2025-12-31
Location Description: Sullivant Public Safety Center
Project Summary:  Installation of parking canopy along west side of Sullivant

Areas Impacted: Minimal pedestrian impact, police parking will be disrupted.

Project Name: University Union East Entrance Door Upgrades

Project Manager: Roberto Rubio
Project Start Date: 2025-09-01
Project End Date: 2025-12-31
Location Description: East Vestibule Entrance at University Union
Project Summary:  Upgrading door system in entrance vestibule

Areas Impacted: Pedestrian access to and from the East Vestibule entrance will be temporarily redirected.

Project Name: Pollinative Prairie Walkway

Project Manager: Brandon Lacy
Project Start Date: 2025-08-04
Project End Date: 2025-09-26
Location Description: Discovery Park Pollinative Prairie
Project Summary:  Addition of covered sidewalk and benches at Pollinative Prairie at Discovery Park campus

Areas Impacted: July 30 controlled burn event will temporarily restrict parking at Discovery  Park.

July 2025

Bonnie Brae St Widening

Project Manager: City of Denton
Start Date: 2024-01-01
End Date: 2026-12-31
Location: Bonnie Brae Street, from Airport Rd to Roselawn Dr

Summary: Installation of underground utilities and roadway expansion to four-lane divided highway.

Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

Science and Tech. Building
Project Manager: Jay Henson, UNT System
Start Date: 2024-01-17
End Date: 2026-09-01
Location: Lot 7, between W Mulberry Street and W Sycamore Street.

Summary: Construction of new Science and Tech building.

Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

Intramural Fields Lighting and Irrigation Installation
Project Manager: Herman McKeiver, Yaggi Engineering
Start Date: 2024-08-01
End Date: 2025-09-01
Location: Intramural Fields at Bonnie Brae and Prairie

Summary: Construction of new field lighting and irrigation systems for intramural fields

Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street.

Discovery Park Fire Piping Replacement
Project Manager: Carl Parsons, UNT
Start Date: 2025-02-03
End Date: 2026-08-04
Location: Discovery Park

Summary: Fire piping to be replaced around building exterior, interior, and installation of water pumps for expanded sprinkler system

Parking lots and sidewalks leading to Discovery Park will be impacted. Trenches dug in phases around the building exterior.

Softball Clubhouse Construction
Project Manager: Jay Henson, UNT System
Start Date: 2025-02-03
End Date: 2025-12-31
Location: Mean Green Village Softball Field

Summary: Improvement of dugouts and construction of new club house and offices.

Use of softball fields and batting facilities will be disrupted during construction.

Mulberry St Construction
Project Manager: City of Denton
Start Date: 2024-12-03
End Date: 2025-07-30
Location: Mulberry Street

Summary: Upgrading city water and sewer lines and street reconstruction.

Mulberry St between Welch St and Bernard St. May impact access to Art Annex, University Machine Shop, and Lot 55.

Welch St Construction
Project Manager: City of Denton
Start Date: 2025-03-13
End Date: 2025-07-15
Location: Welch St between Highland St and Eagle Dr

Summary: Road reconstruction

No automobile traffic on Welch St between Eagle and Highland. Westbound traffic may cross at Maple St. No sidewalk accessible across Maple St or Highland St.

Gateway Class Ring Sculpture
Project Manager: Brandon Lacy
Start Date: 2025-05-05
End Date: 2025-05-30
Location: Gateway Center

Summary: Installation of UNT Class Ring sculpture and base with lighting and drainage

Sidewalk beneath the arch of Gateway Center will be partially blocked, building entrances will remain accessible.

Chilton Hall Sidewalk Expansion
Project Manager: Brandon Lacy
Start Date: 2025-05-12
End Date: 2025-07-31
Location: Chilton Hall East Side

Summary: Landscaping upgrades and widening of sidewalk in front of Chilton Hall along Avenue C.

No sidewalk access along Avenue C. East entrance to Chilton Hall 2nd Floor will not be accessible.

Ave D and Chestnut Street Construction
Project Manager: City of Denton
Start Date: 2025-05-14
End Date: 2025-08-15
Location: Intersection of Avenue D and Chestnut Street

Summary: Road reconstruction

Ave D between Chestnut and Mulberry, Chestnut Street between Ave D and Ave C. Lot 5 accessible via Sycamore. No sidewalk access along Ave D or Chestnut. Disrupted access for Chestnut and Chilton Halls.

Union Circle Realignment
Project Manager: City of Denton
Start Date: 2025-05-14
End Date: 2025-10-01
Location: Union Circle

Summary: Street reconstruction and realignment. Traffic flow on Union Circle will be reversed.

Union Circle. Impacts access to the University Union, Matthews Hall Annex, Union Circle Garage, Radio TV and Performing Arts Building, Lot 50, and Lot 37.

Replace Lot 20 Sanitary Sewer
Project Manager: Randy Salsman
Start Date: 2025-05-12
End Date: 2025-08-18
Location: Lot 20 Center Lane

Summary: Replace portion of sewer line infrastructure

Portion of the central access lane in Lot 20 will be closed and traffic redirected. Bus service to Lot 20 will be minimally impacted.

Hickory Street Landscaping Renovation
Project Manager: Brandon Lacy
Start Date: 2025-06-09
End Date: 2025-08-15
Location: Lawns and sidewalks north of Language, Auditorium, and Hickory Hall

Summary: Renovate landscaping

Sidewalk access will be blocked on the north side of Language, Auditorium, and Hickory Hall.

Highland Garage Landscaping Renovation
Project Manager: Brandon Lacy
Start Date: 2025-06-02
End Date: 2025-08-08
Location: Highland Street Parking Garage

Summary: Maintenance of trees and landscaping and updating irrigation

Sidewalk will be closed between Highland Street and the garage. Access to the garage and crosswalk will not be disrupted.

Chestnut Hall Landscaping Renovation
Project Manager: Brandon Lacy
Start Date: 2025-06-02
End Date: 2025-08-08
Location: South side of Chestnut Hall

Summary: Renovation of landscaping and irrigation south of Chestnut Hall

Pedestrian access to Chestnut Hall from the South may be disrupted.

Welch Street Construction
Project Manager: City of Denton
Start Date: 2025-07-07
End Date: 2025-10-01
Location: Welch Street between Mulberry and Sycamore

Summary: Utilities replacement and road reconstruction

No automobile traffic on Welch St between Mulberry and Sycamore. No pedestrian crosswalk.

June 2025

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-03-13

Project End Date: 2025-06-11

Location Description: Welch St between Highland St and Eagle Dr

Project Summary:  Road reconstruction

Areas Impacted: No automobile traffic on Welch St between Eagle and Highland. Westbound traffic may cross at Maple St. No sidewalk accessible across Maple St or Highland St.

Project Name: Mulberry St Construction

Project Manager: City of Denton

Project Start Date: 2024-12-03

Project End Date: 2025-07-03

Location Description: Mulberry Street

Project Summary:  Upgrading city water and sewer lines and street reconstruction.

Areas Impacted: Mulberry St between Welch St and Bernard St. May impact access to Art Annex, University Machine Shop, and Lot 55.

Project Name: Prairie St Construction

Project Manager: City of Denton

Project Start Date: 2025-03-25

Project End Date: 2025-09-25

Location Description: Prairie St between Bernard St and Welch St

Project Summary:  Replace water and sewer lines and street reconstruction

Areas Impacted: Automobile traffic will be disrupted. Lots 47 and 39 impacted.  Pedestrian and parking access to Welch Street Complex will be disrupted. No sidewalk access across Prairie St.

Project Name: Union Circle Realignment

Project Manager: City of Denton

Project Start Date: 2025-05-14

Project End Date: 2025-09-30

Location Description: Union Circle

Project Summary:  Street reconstruction and realignment. Traffic flow on Union Circle will be reversed.

Areas Impacted: Union Circle. Impacts access to the University Union, Matthews Hall Annex, Union Circle Garage, Radio TV and Performing Arts Building, Lot 50, and Lot 37.

 Project Name: Avenue A Utilities

Project Manager: Tracy Beck & Scott Fettig - City of Denton

Project Start Date: 2025-02-21

Project End Date: 2025-06-26

Location Description: Avenue A between Eagle Dr and Maple St

Project Summary:  Replace water and sewer lines and street reconstruction

Areas Impacted: Project area open for traffic for resident move-out. Construction will resume May 12th. Closure of Avenue A between Maple and Eagle and Maple Street between Central and Avenue A. No pedestrian access.

 Project Name: Ave D and Chestnut Street Construction

Project Manager: City of Denton

Project Start Date: 2025-05-14

Project End Date: 2025-08-31

Location Description: Intersection of Avenue D and Chestnut Street

Project Summary:  Street reconstruction

Areas Impacted: Ave D between Chestnut and Mulberry, Chestnut Street between Ave D and Ave C. Lot 5 accessible via Sycamore. No sidewalk access along Ave D or Chestnut. Disrupted access for Chestnut and Chilton Halls

 Project Name: Bonnie Brae St Widening

Project Manager: City of Denton

Project Start Date: 2024-01-01

Project End Date: 2026-12-31

Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr

Project Summary:  Installation of underground utilities and roadway expansion to four-lane divided highway.

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

Project Name: Replace Lot 20 Sanitary Sewer

Project Manager: Randy Salsman

Project Start Date: 2025-05-12

Project End Date: 2025-08-18

Location Description: Lot 20 Center Lane

Project Summary:  Replace portion of sewer line infrastructure

Areas Impacted: Portion of the central access lane in Lot 20 will be closed and traffic redirected. Bus service to Lot 20 will be minimally impacted.

Project Name: Hurley Courtyard Landscaping

Project Manager: Brandon Lacy

Project Start Date: 2025-05-19

Project End Date: 2025-07-11

Location Description: North side of Hurley Administration Building

Project Summary:  Renovations to the entry courtyard

Areas Impacted: Entrances to Hurley Administration will not be accessible for duration of project. Accessible entrance available on South side of building.

Project Name: Chilton Hall Sidewalk Expansion

Project Manager: Brandon Lacy

Project Start Date: 2025-05-12

Project End Date: 2025-07-31

Location Description: Chilton Hall East Side

Project Summary:  Landscaping upgrades and widening of sidewalk in front of Chilton Hall along Avenue C.

Areas Impacted: No sidewalk access along Avenue C. East entrance to Chilton Hall 2nd Floor will not be accessible.

Project Name: Chestnut Hall Landscaping Renovation

Project Manager: Brandon Lacy

Project Start Date: 2025-06-02

Project End Date: 2025-08-08

Location Description: South side of Chestnut Hall

Project Summary:  Renovation of landscaping and irrigation south of Chestnut Hall

Areas Impacted: Pedestrian access to Chestnut Hall from the South may be disrupted.

Project Name: Hickory Street Landscaping Renovation

Project Manager: Brandon Lacy

Project Start Date: 2025-06-09

Project End Date: 2025-08-15

Location Description: Lawns and sidewalks north of Language, Auditorium, and Hickory Hall

Project Summary:  Renovate landscaping

Areas Impacted: Sidewalk access will be blocked on the north side of Language, Auditorium, and Hickory Hall.

Project Name: Highland Garage Landscaping Renovation

Project Manager: Brandon Lacy

Project Start Date: 2025-06-02

Project End Date: 2025-08-08

Location Description: Highland Street Parking Garage

Project Summary:  Maintenance of trees and landscaping and updating irrigation

Areas Impacted: Sidewalk will be closed between Highland Street and the garage. Access to the garage and crosswalk will not be disrupted.

Project Name: Discovery Park Fire Piping Replacement

Project Manager: Carl Parsons, UNT

Project Start Date: 2025-02-03

Project End Date: 2026-08-04

Location Description: Discovery Park

Project Summary:  Fire piping to be replaced around building exterior, interior, and installation of water pumps for expanded sprinkler system

Areas Impacted: Parking lots and sidewalks leading to Discovery Park will be impacted. Trenches dug in phases around the building exterior.

Project Name: Science and Tech. Building

Project Manager: Jay Henson, UNT System

Project Start Date: 2024-09-01

Project End Date: 2026-09-01

Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.

Project Summary:  Construction of new Science and Tech. building.

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

Project Name: Softball Clubhouse Construction

Project Manager: Jay Henson, UNT System

Project Start Date: 2025-02-03

Project End Date: 2025-12-31

Location Description: Mean Green Village Softball Field

Project Summary:  Improvement of dugouts and construction of new club house and offices.

Areas Impacted: Use of softball fields and batting facilities will be disrupted during construction.

 Project Name: Intramural Fields Lighting and Irrigation Installation

Project Manager: Herman McKeiver, Yaggi Engineering

Project Start Date: 2024-08-01

Project End Date: 2025-09-01

Location Description: Intramural Fields at Bonnie Brae and Prairie

Project Summary:  Construction of new field lighting and irrigation systems for intramural fields

Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street.

May 2025

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-03-13

Project End Date: 2025-05-30

Location Description: Welch St between Highland St and Eagle Dr

Project Summary: Road reconstruction

Areas Impacted: No automobile traffic on Welch St between Eagle and Highland. Westbound traffic may cross at Maple St. No sidewalk accessible across Maple St or Highland St.

 

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-04-23

Project End Date: 2025-07-15

Location Description: Welch Street, between W Highland St and W Prairie St

Project Summary: Road reconstruction

Areas Impacted: Automobile and pedestrian traffic will be disrupted for the duration of the project. No crosswalk access at Welch and Prairie.

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-02-01

Project End Date: 2025-04-26

Location Description: Welch St between W Sycamore St and W Chestnut St/Union Circle

Project Summary: Road to be reconstructed

Areas Impacted: Automobile and pedestrian traffic will be disrupted for duration of the project. No crosswalk access at Chestnut or Sycamore St. Access to Lots 55 and 54 redirect via Bernard St.

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-04-23

Project End Date: 2025-07-14

Location Description: Welch St between W Sycamore St and W Mulberry St

Project Summary: Road reconstruction

Areas Impacted: Automobile and pedestrian traffic will be disrupted for duration of the project. No crosswalk access at Sycamore St. Access to Lots 55 and 54 redirect via Bernard St.

 

Project Name: Mulberry St Construction

Project Manager: City of Denton

Project Start Date: 2024-12-03

Project End Date: 2025-06-01

Location Description: Mulberry Street

Project Summary: Upgrading city water and sewer lines and street reconstruction.

Areas Impacted: Mulberry St between Welch St and Bernard St. May impact access to Art Annex, University Machine Shop, and Lot 55.

 

Project Name: Prairie St Construction

Project Manager: City of Denton

Project Start Date: 2025-03-25

Project End Date: 2025-09-25

Location Description: Prairie St between Bernard St and Welch St

Project Summary: Replace water and sewer lines and street reconstruction

Areas Impacted: Automobile traffic will be disrupted. Lots 47 and 39 impacted.  Pedestrian and parking access to Welch Street Complex will be disrupted. No sidewalk access across Prairie St.

 

Project Name: Union Circle Realignment

Project Manager: City of Denton

Project Start Date: 2025-05-14

Project End Date: 2025-09-30

Location Description: Union Circle

Project Summary: Street reconstruction and realignment. Traffic flow on Union Circle will be reversed.

Areas Impacted: Union Circle. Impacts access to the University Union, Matthews Hall Annex, Union Circle Garage, Radio TV and Performing Arts Building, Lot 50, and Lot 37.

 

Project Name: Avenue A Utilities

Project Manager: Tracy Beck & Scott Fettig - City of Denton

Project Start Date: 2025-02-21

Project End Date: 2025-06-26

Location Description: Avenue A between Eagle Dr and Maple St

Project Summary: Replace water and sewer lines and street reconstruction

Areas Impacted: Automobile traffic will be disrupted. Intersection closed at Maple Street. No pedestrian access across Avenue A at Maple Street. Access to lots 33 and 32 will be impacted.

 

Project Name: Ave D and Chestnut Street Construction

Project Manager: City of Denton

Project Start Date: 2025-05-14

Project End Date: 2025-08-31

Location Description: Intersection of Avenue D and Chestnut Street

Project Summary: Street reconstruction

Areas Impacted: Avenue D between Chestnut Street and West Sycamore Street and Chestnut Street between Avenue D and Avenue C. Will impact access to Physical Education, Pohl Rec Center, Chestnut, Chilton, Lot 5 and 4.

 

Project Name: Bonnie Brae St Widening

Project Manager: City of Denton

Project Start Date: 2024-01-01

Project End Date: 2026-12-31

Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr

Project Summary: Installation of underground utilities and roadway expansion to four-lane divided highway.

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

 

Project Name: Science and Tech. Building

Project Manager: Jay Henson, UNT System

Project Start Date: 2024-09-01

Project End Date: 2026-09-01

Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.

Project Summary: Construction of new Science and Tech. building.

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

Project Name: Performing Arts Center Electrical

Project Manager: Carl Parsons

Project Start Date: 2025-04-18

Project End Date: 2025-05-05

Location Description: Eagle Drive at I-35 and North side of Murchison Performing Arts Center

Project Summary: Installation of subsurface electrical lines.

Areas Impacted: Pedestrian access to Murchison Performing Arts Center and Annex will be disrupted while trench is open. Parking at Performing Arts Annex will be disrupted throughout the project. Lot 20 will be open.

 

Project Name: Discovery Park Fire Piping Replacement

Project Manager: Carl Parsons, UNT

Project Start Date: 2025-02-03

Project End Date: 2026-08-04

Location Description: Discovery Park

Project Summary: Fire piping to be replaced around building exterior, interior, and installation of water pumps for expanded sprinkler system

Areas Impacted: Parking lots and sidewalks leading to Discovery Park will be impacted. Trenches dug in phases around the building exterior.

 

Project Name: Intramual Fields Lighting and Irrigation Installation

Project Manager: Herman McKeiver, Yaggi Engineering

Project Start Date: 2024-08-01

Project End Date: 2025-09-01

Location Description: Intramural Fields at Bonnie Brae and Prairie

Project Summary: Construction of new field lighting and irrigation systems for intramural fields

Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street.

 

Project Name: Softball Clubhouse Construction

Project Manager: Jay Henson, UNT System

Project Start Date: 2025-02-03

Project End Date: 2025-12-31

Location Description: Mean Green Village Softball Field

Project Summary: Improvement of dugouts and construction of new club house and offices.

Areas Impacted: Use of softball fields and batting facilities will be disrupted during construction.

 

Project Name: Lot 20 Sewer Work

Project Manager: Vince Stippec

Project Start Date: 2025-05-12

Project End Date: 2025-07-01

Location Description: Lot 20 Center Lane

Project Summary: Replacement of sewer line

Areas Impacted: Portion of the central access lane in Lot 20 will be closed and traffic redirected. Bus service to Lot 20 will be minimally impacted.

 

Project Name: Chilton Hall Sidewalk Expansion

Project Manager: Brandon Lacy

Project Start Date: 2025-05-12

Project End Date: 2025-07-31

Location Description: Chilton Hall East Side

Project Summary: Landscaping upgrades and widening of sidewalk in front of Chilton Hall along Avenue C.

Areas Impacted: No sidewalk access along Avenue C. East entrance to Chilton Hall 2nd Floor will not be accessible.

 

Project Name: Gateway Class Ring Sculpture

Project Manager: Brandon Lacy

Project Start Date: 2025-05-05

Project End Date: 2025-05-30

Location Description: Gateway Center

Project Summary: Installation of UNT Class Ring sculpture and base with lighting and drainage

Areas Impacted: Sidewalk beneath the arch of Gateway Center will be partially blocked, building entrances will remain accessible.

April 2025

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-03-13

Project End Date: 2025-05-30

Location Description: Welch St between Highland St and Eagle Dr

Project Summary:  Road reconstruction

Areas Impacted: No automobile traffic on Welch St between Eagle and Highland. Westbound traffic may cross at Maple St. No sidewalk accessible across Maple St or Highland St.

 

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-02-01

Project End Date: 2025-04-26

Location Description: Welch St between W Mulberry St and W Chestnut St/Union Circle

Project Summary:  Road reconstruction

Areas Impacted: Welch St closed between Chestnut St and Sycamore St until the portion of Welch St between W Mulberry and W Hickory is completed. Traffic to Lot 50 redirected through Union Circle.

 

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-01-06

Project End Date: 2025-04-02

Location Description: Welch Street, between W Prairie St and Chestnut St

Project Summary:  Road reconstruction

Areas Impacted: Vehicular and pedestrian traffic will be disrupted for the duration of the project. Access to Lot 47 will be blocked.

 

Project Name: Mulberry St Construction

Project Manager: City of Denton

Project Start Date: 2024-12-03

Project End Date: 2025-06-01

Location Description: Mulberry Street

Project Summary:  Upgrading city water and sewer lines and street reconstruction

Areas Impacted: Mulberry St between Welch St and Bernard St. May impact access to Art Annex, University Machine Shop, and Lot 55.

 

Project Name: Prairie St Construction

Project Manager: City of Denton

Project Start Date: 2025-03-25

Project End Date: 2025-05-12

Location Description: Prairie St between Bernard St and Welch St

Project Summary:  Upgrading city water and sewer lines and street reconstruction

Areas Impacted: Automobile traffic will be disrupted. Lots 47 and 39 impacted.  Pedestrian and parking access to Welch Street Complex will be disrupted. No sidewalk access across Prairie St.

 

Project Name: Bonnie Brae St Widening

Project Manager: City of Denton

Project Start Date: 2024-01-01

Project End Date: 2026-12-31

Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr

Project Summary:  Installation of underground utilities and roadway expansion to four-lane divided highway

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

 

Project Name: Science and Tech. Building

Project Manager: Jay Henson, UNT System

Project Start Date: 2024-09-01

Project End Date: 2026-09-01

Location Description: Lot 7, between W Mulberry Street and W Sycamore Street

Project Summary:  Construction of new Science and Tech. building

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

 

Project Name: Performing Arts Center Electrical

Project Manager: Carl Parsons

Project Start Date: 2025-04-18

Project End Date: 2025-05-05

Location Description: Eagle Drive at I-35 and North side of Murchison Performing Arts Center

Project Summary:  Installation of subsurface electrical lines

Areas Impacted: Pedestrian access to Murchison Performing Arts Center and Annex will be disrupted while trench is open. Parking at Performing Arts Annex will be disrupted throughout the project. Lot 20 will be open.

 

Project Name: Discovery Park Fire Piping Replacement

Project Manager: Carl Parsons, UNT

Project Start Date: 2025-02-03

Project End Date: 2026-08-04

Location Description: Discovery Park

Project Summary:  Fire piping to be replaced around building exterior, interior, and installation of water pumps for expanded sprinkler system

Areas Impacted: Parking lots and sidewalks leading to Discovery Park will be impacted. Trenches dug in phases around the building exterior.

 

Project Name: Intramural Fields Lighting and Irrigation Installation

Project Manager: Herman McKeiver

Project Start Date: 2024-08-01

Project End Date: 2025-09-01

Location Description: Intramural Fields at Bonnie Brae and Prairie

Project Summary:  Construction of new field lighting and irrigation systems for intramural fields

Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street.

 

Project Name: Softball Clubhouse Construction

Project Manager: Jay Henson, UNT System

Project Start Date: 2025-02-03

Project End Date: 2025-12-31

Location Description: Mean Green Village Softball Field

Project Summary:  Improvement of dugouts and construction of new club house and offices.

Areas Impacted: Use of softball fields and batting facilities will be disrupted during construction.

March 2025

Not available

February 2025

Project Name: Welch St Utilities

Project Manager: City of Denton

Project Start Date: 2024-11-20

Project End Date: 2025-02-19

Location Description: Welch St between W Hickory St and W Mulberry St

Project Summary:  Replacement of water and sewer lines.

Areas Impacted: Through traffic is blocked. Intersections to remain open.

 

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-01-06

Project End Date: 2025-04-02

Location Description: Welch Street, between W Prairie St and Chestnut St

Project Summary:  Road reconstruction

Areas Impacted: Vehicular and pedestrian traffic will be disrupted for the duration of the project

 

Project Name: Welch St Construction

Project Manager: City of Denton

Project Start Date: 2025-02-01

Project End Date: 2025-04-26

Location Description: Welch St between W Mulberry St and W Chestnut St/Union Circle

Project Summary:  Road to be reconstructed

Areas Impacted: Welch St closed between Chestnut St and Sycamore St until the portion of Welch St between W Mulberry and W Hickory is completed. Traffic to Lot 50 redirected through Union Circle.

 

Project Name: Mulberry St Construction

Project Manager: City of Denton

Project Start Date: 2024-12-03

Project End Date: 2025-06-02

Location Description: Mulberry Street

Project Summary:  Upgrading city water and sewer lines and street reconstruction.

Areas Impacted: Mulberry St between Welch St and Bernard St. May impact access to Art Annex, University Machine Shop, and Lot 55.

 

Project Name: Bonnie Brae St Widening

Project Manager: City of Denton

Project Start Date: 2024-01-01

Project End Date: 2026-12-31

Location Description: Bonnie Brae Street, from Airport Rd to Roselawn Dr

Project Summary:  Installation of underground utilities and roadway expansion to four-lane divided highway.

Areas Impacted: Vehicular and pedestrian traffic will be intermittently disrupted for the duration of the project.

 

Project Name: Science and Tech. Building

Project Manager: Hannah Aikin

Project Start Date: 2024-09-01

Project End Date: 2026-09-01

Location Description: Lot 7, between W Mulberry Street and W Sycamore Street.

Project Summary:  Construction of new Science and Tech. building.

Areas Impacted: Lot 7 and adjacent sidewalks will be disrupted for the duration of the project.

 

Project Name: Intramural Fields Lighting and Irrigation Installation

Project Manager: Herman McKeiver, Yaggi Engineering

Project Start Date: 2024-08-01

Project End Date: 2025-09-01

Location Description: Intramural Fields at Bonnie Brae and Prairie

Project Summary:  Construction of new field lighting and irrigation systems for intramural fields

Areas Impacted: Intramural Fields on North Bonnie Brae Street between I-35 frontage road and Prairie Street

 

Project Name: Discovery Park Fire Piping Replacement

Project Manager: Carl Parsons, UNT

Project Start Date: 2025-02-03

Project End Date: 2026-08-04

Location Description: Discovery Park

Project Summary:  Fire piping to be replaced around building exterior, interior, and installation of water pumps for expanded sprinkler system

Areas Impacted: Discovery Park and parking lots

 

Project Name: Avenue A Utilities

Project Manager: Tracy Beck & Scott Fettig - City of Denton

Project Start Date: 2025-02-21

Project End Date: 2025-06-26

Location Description: Avenue A between Eagle Dr and Maple St

Project Summary:  Replace water and sewer lines and street reconstruction

Areas Impacted: Automobile traffic will be disrupted. Intersecting streets to remain open. Access to Lots 33 and 32 will be impacted.

January 2025

Not available